Project Performance Evaluation Using Critical Path Method and Earned Value Management: A Comparative Analysis of Road Maintenance Projects in the 4th District of Camarines Sur
Downloads
Road maintenance projects often face delays and budget overruns due to dispersed works, constrained time windows, and resource limitations. This study evaluates the comparative effectiveness of the Critical Path Method (CPM) and Earned Value Management (EVM), including Earned Schedule (ES), in monitoring the performance of road maintenance projects in the 4th District of Camarines Sur, Philippines. A descriptive–comparative design was applied, analyzing five purposively selected projects through documentary analysis, schedule reconstruction, EVM computation, and key informant validation. Findings reveal that CPM obtained a weighted mean rating of 4.3, emphasizing its strength in identifying critical activities and forecasting schedule delays, while EVM registered a mean of 4.4, highlighting its greater utility in cost efficiency and integrated performance analysis. Notably, the integrated CPM–EVM framework achieved the highest rating of 4.8, underscoring its superior usefulness and potential for institutional adoption in infrastructure project monitoring. The study recommends that the Department of Public Works and Highways (DPWH) institutionalize CPM–EVM integration to enhance accountability, early warning systems, and transparency in project delivery.
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12–23.
https://doi.org/10.1177/875697280303400403
Bongaerts, L., Vanhoucke, M., & Coelho, J. (2025). Comparative analysis of earned value management techniques in project control. Scientific Reports, 15(1), 11539.
https://doi.org/10.1038/s41598-025-96425-9
Creswell, J. W., & Creswell, J. D. (2018). Research design: Qualitative, quantitative, and mixed methods approaches (5th ed.). SAGE Publications.
Department of Public Works and Highways (DPWH). (2022). Annual procurement plan and project monitoring reports. Department of Public Works and Highways, Republic of the Philippines.
Department of Public Works and Highways (DPWH). (2023). Project completion reports. Department of Public Works and Highways, Republic of the Philippines.
Department of Public Works and Highways. (2022). Annual procurement plan and project monitoring reports. DPWH.
Fleming, Q. W., & Koppelman, J. M. (2016). Earned value project management (4th ed.). Project Management Institute.
Gharaibeh, N. G., Chatterjee, D., & Cai, X. (2023). Simplified earned value analysis method for highway construction projects. Transportation Research Record, 2677(4), 1–12.
https://doi.org/10.1177/03611981231156743
Kelley, J. E., & Walker, M. R. (1959). Critical-path planning and scheduling. Proceedings of the Eastern Joint Computer Conference, 160–173.
https://doi.org/10.1145/1460299.1460318
Kelley, J. E., Jr., & Walker, M. R. (1959). Critical-path planning and scheduling. In Proceedings of the Eastern Joint Computer Conference (pp. 160–173).
IRE.
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Wiley.
Lipke, W. (2003). Earned schedule. The Measurable News, (Summer), 31–36. Retrieved from http://www.earnedschedule.com
Lipke, W. (2003). Schedule is different. The Measurable News, (Spring), 31–34.
Lipke, W. (2014). Introduction to earned schedule. PM World Journal, 3(3), 1–15.
Project Management Institute (PMI). (2021). A guide to the project management body of knowledge (PMBOK® Guide) (7th ed.). Project Management Institute.
Rimando, R. S. A., & Muhi, M. M. (2025). Sectoral occupational safety compliance of selected construction projects in the 4th District of Camarines Sur. Global Journal of Technology, Development, and Social Innovations, 5(1), 14–29. https://doi.org/10.62718/vmca.tech-gjtdsi.5.1.SC-0725-008
Transportation Research Board. (1980).
Application of critical path method to highway construction projects. TRB.
Vanhoucke, M. (2012). Project management with dynamic scheduling: Baseline scheduling, risk analysis and project control. Springer.
Wingate, P. J. F. (1970). The use of critical path method to plan and control road construction projects. Proceedings of the Institution of Civil Engineers, 45(3), 423–438.