Design Optimization of a Run-Of-River Small Hydropower Plant: A Case Study of Mabula Kapi Site
Downloads
Prior to construction, small or large hydropower plants undergo feasibility studies, which involve technical, economic, financial, social, and environmental aspects. Technical studies, particularly, include various engineering disciplines. This study sought to conduct a component of technical feasibility studies, focused on design optimization of the turbine-plant capacity size for a run-of-river case study called Mabula Kapi, on Kaombe River, Serenje, Zambia. The study method used computational modelling, simulation, and optimization techniques, and used secondary data from previous site. A prefeasibility study conducted earlier had underestimated the turbine-plant capacity owing to underestimated discharge data, owing to lack of site gauging station. A less accurate discharge estimation method involving transposition from a gauged similar catchment had been used. A later feasibility-level site hydrological study found improved discharge data. Riding on the improved discharge data, this study found the following optimised plant design parameters based on plant design discharge of 6.20 m3/s: Installed capacity of 10.20 MW; Annual energy production of 42 GWh; Capacity factor of 47.1%; 3 x Pelton wheel of 272 rpm speed, 2.1 m diameter, 2-nozzles of diameter 0.16 m each, 21 buckets of 0.58m width each; and 3 x 4 MVA generators of 50Hz, 22-poles, and 11kV.
Acharya, K. K., 2019. Fluid Machines Chapter 3: Water Turbine - Pelton Turbine. [Online]
Available at: https://www.slideshare.net/AwanKhadka2/4-pelton-turbine
[Accessed 18 July 2023].
Adejumobi, I. & Shobayo, D., 2015. Optimal Selection of Hydraulic Turbines for Small Hydro Electric Power Generation - A Case Study of Opeki River, South Western Nigeria. Nigerian Journal of Technology, 34(3), pp. 530-537.
Alternate Hydro Energy Centre, 2012. Standards/Manuals/Guidelines for Small Hydro Development: Electromechanical 3.2 Selection of Generators and Excitation Systems , Roorkee: Indian Institute of Technology Roorkee.
Alternate Hydro Energy Centre, 2012. Standards/Manuals/Guidelines for Small Hydropower Development: 3.1 Electro-Mechanical 3-Selection of Turbine and Governing System, Roorkee: Indian Institute of Technology Roorkee.
Deb, D., Dey, R. & Balas, V. E., 2019. Engineering Research Methodology: A Practical Insight for Researchers. Singapore: Springer Nature Singapore Pte Ltd.
European Small Hydropower Association, 2004. Guide on How to Develop a Small Hydropower Plant, Clavier: ESHA.
Goddard, A., 2021. An Investor's Guide to Hydropower in Africa, London: Addleshaw Goddard LLP.
Government Republic of Zambia, 2006. Vision 2030 - A Prosperous Middle-Income Nation by 2030, Lusaka: Government Republic of Zambia.
International Hydropower Association, 2023. 2023 World Hydropower Outlook, London: International Hydropower Association.
International Renewable Energy Agency, 2015. Hydropower: Technology Brief, Abu Dhabi: International Renewable Energy Agency.
International Renewable Energy Agency, 2022. Renewable Power Generation Costs in 2021, Abu Dhabi: International Renewable Energy Agency.
Kalina, T., Illes, L., Jurkovic, M. & Luptak, V., 2021. Development and Design Optimisation of a Small Floating Hydroelectric Power Plant. Acta Polytechnica Hungarica, 18(10), pp. 43-63.
Killingtveit, 2018. Hydropower. In: T. M. Letcher, ed. Managing Global Warming: An Interface of Technology and Human Issues. Amsterdam: Elsevier Academic Press, pp. 265-315.
Ministry of Energy, 2019. National Energy Policy 2019, Lusaka: Government Republic of Zambia.
Ministry of Energy, 2019. National Energy Policy 2019, Lusaka: Government Republic of Zambia.
Ministry of Energy, 2022. Renewable Energy Strategy and Action Plan, Lusaka: Government Republic of Zambia.
Mukuka, R., 2022. Improving Discharge Prediction for Poorly Gauged Hydropower Potential Sites - A Case of Mabula Kapi Site , Lusaka: MEng Thesis, The University of Zambia.
Nasir, B. A., 2014. Design Considerations of Micro-Hydro-Electric Power Plant. Energy Procedia, Volume 50, pp. 19-29.
Nasir, B. A., 2021. Design Aspects of Small-Hydropower Plant. Journal of Energy Research and Reviews, 9(2), pp. 1-9.
Natural Resources Canada, 2004. RETScreen Software Online User Manual. Ottawa: Ministry of Natural Resources Canada.
Otuagoma, S., 2016. Turbine Selection Criteria for Small Hydropower Development – The River Ethiope Experience. International Journal of Latest Research in Engineering and Technology, 2(5), pp. 34-40.
Rajput, R., 2015. A Textbook of Fluid Mechanics and Hydraulic Machines. 6th ed. New Delhi : S. Chand & Company Ltd.
RETScreen International, 2005. Clean Energy Project Analysis: RETScreen Engineering and Cases Textbook. 3rd ed. Toronto: Ministry of Natural Resources Canada.
Tefera, W. M. & Kasiviswanathan, K., 2022. A Global-scale Hydropower Potential Assessment and Feasibility Evaluations. Water Resources and Economics, 38(2022), pp. ISSN 2212-4284.
Temiz, A., 2013. Decision Making on Turbine Types and Capacities for Run-of-River Hydroelectric Power Plants: A Case Study on Eglence-1 HEPP. Masters Thesis: Izmir Institute of Technology.
United Nations Industrial Development Organisation, 2019. Technical Guidelines for the Development of Small Hydropower Plants: Design, Vienna: UNIDO and INSHIP.
United Nations Industrial Development Organisation, 2019. Technical Guidelines for the Development of Small Hydropower Plants: Design - Part 1 Site Selection Planning, Vienna: UNIDO/INSHIP.
United Nations Industrial Development Organisation, 2019. World Small Hydropower Development Report 2019, Vienna: United Nations Development Organisation.
US Army Corps of Engineers, 1985. Hydro Plant Sizing, Washington DC: US Army Corps of Engineers.
Vasic, M., Matejic, M. & Blagoje-vic, M., 2018. Influence Analysis of Selected Turbine to Working Characteristics of Small Hydropower Plants. Machine Design, 10(1), pp. 11-16.
Yusuf, K., Alkhaly, Y. R. & Amalia, A., 2022. Optimization of Small Run-of-River Hydropower. International Journal of Engineering, Science & InformationTechnology, 2(3), pp. 58-63.
Zaw Oo, T., N, N. & Khaing, C., 2019. Design Calculation of Pelton Turbine for 220 kW. International Journal of Scientific and Research Publications,, 9(7), pp. 218-224.
ZESCO, 2018. Preafeasibility Study for the Proposed Kaombe Small-Hydro Electric Power Plant, Lusaka: ZESCO.
Zhamalovich, A. et al., 2013. Selection of Generator for the Micro Hydro Power Plant. American-Eurasian Journal of Scientific Research, 8(3), pp. 104-108.
Zhang, Q. F., Uria-Martinez, R. & Saulsbury, B., 2013. Technical and Economic Feasibility Assessment of Small Hydropower Development in the Deschutes River Basin, Oak Ridge: Oak Ridge National Laboratory, U.S. Department of Energy.
Zhou, Y. et al., 2015. A Comprehensive View of Global Potential for Hydro-generated Electricity. Energy & Environment , 8(2015), pp. 2622-2633.