Construction Material Waste at the “Apartment X” Project in Bekasi, West Java, Indonesia
Downloads
The implementation of a construction project activity is a lengthy process that is fraught with numerous issues and challenges. The presence of a lot of material waste is one of them. Waste material in the form of concrete rebar was also discovered at the “Apartment X” project in Bekasi, West Java. This research was carried out through interviews, questionnaire distribution, and observation. The findings of the research revealed that the largest percentage of concrete rebar waste in several columns work is D19 rebar waste with a percentage of 18.35%; then the largest percentage in partial wall of STP work is D16 rebar waste with a percentage of 1.29%. Carelessness and worker mistakes, followed by lack of workforce skills, are the factors that influence the occurrence of concrete rebar waste at the “Apartment X” project in Bekasi, West Java, the contractor should have a good quality control system and supervise the workers involved in concrete rebar properly in order to minimize errors that may result in the occurrence of excessive waste. The contractor should also ensure that all parties involved with concrete rebar, from the engineering side to the field implementer, have the capacity to carry out the work that will be assigned.
Al-Moghany, S. S. (2006). Managing and Minimizing Construction Waste in Gaza Strip. The Islamic University of Gaza.
Alwi, S., Hampson, K. D., & Mohamed, S. A. (2002). Waste In Indonesian Construction Projects. Proceedings of The 1st International Conference of CIB W107 - Creating a Sustainable Construction Industry in Developing Countries, 305–315.
Apni, N., & Puspasari, V. H. (2019). FAKTOR-FAKTOR PENYEBAB CONSTRUCTION WASTE PADA PROYEK KONSTRUKSI DI KOTA PALANGKA RAYA. Jurnal Teknika, 3(1), 31–42.
Chen, Z., Li, H., & Wong, C. T. C. (2002). An Application of Bar-code System for Reducing Construction Wastes. Automation in Construction, 11(5), 521–533.
Dr. Suparyanto, M.Kes. (2010). Uji Validitas Kuesioner Penelitian.
http://dr-suparyanto.blogspot.com/2010/12/uji-validitas-kuesioner-penelitian.html
Ervianto, W. I. (2005). Manajemen Proyek Konstruksi (Edisi Revisi). Penerbit Andi.
Formoso, C. T., Isatto, E. L., & Hirota, E. H. (1999, July). Method for Waste Control in the Building Industry. Proceedings of the Seventh Annual Conference of the International Group for Lean Construction IGLC-7.
Hadut, A. M., & Koesmargono, K. (2018). Kajian Identifikasi Penyebab Construction Waste pada Kontraktor Di Daerah Yogyakarta dan Kupang. Jurnal Teknik Sipil, 25(3), 237. https://doi.org/10.5614/jts.2018.25.3.9
Kaming, P. F., Raharjo, F., & Wejoseno, H. (2014). CONSTRUCTION WASTE PADA PROYEK-PROYEK KONSTRUKSI DI DAERAH ISTIMEWA YOGYAKARTA,. Prosiding Konferensi Nasional Teknik Sipil (KoNTekS) ke-8, 146–154.
Koskela, L. (1992). Application of the New Production Philosophy to Construction (Technical Report 72). Stanford University.
Polat, G., & Ballard, G. (2004). Waste in Turkish Construction: Need for Lean Construction Techniques. Proceedings of The 12th Annual Conference of the International Group for Lean Construction IGLC-12.
Putra, I. G. P. A. S., Dharmayanti, G. A. P. C., & Dewi, A. A. D. P. (2018). PENANGANAN WASTE MATERIAL PADA PROYEK KONSTRUKSI GEDUNG BERTINGKAT. Jurnal Spektran, 6, 176–185.
Sapitri & Firdaus. (2019). Waste Konstruksi: Identifikasi Potensi dan Penyebabnya Pada Proyek Perumahan Di Pekanbaru. JURNAL SAINTIS, 19(02),79–88. https://doi.org/10.25299/saintis.2019.vol19(02).3904
Skoyles, E. R. (1976). Material Wastage: A Misuse of Resources. Batiment International, Building Research and Practice, 4(4).
Skoyles, E. R., & Skoyles, J. R. (1987). Waste Prevention On Site. Mitchell.